Executive Summary
Facing capacity problems with two items which are manufactured in-house (the Circuit Board A and the I/O Sub C) and past due deliverables of the two item’s component parts, Judy must make decisions on how to address these issues. The accounting and finance department also requested from Judy to provide them with inventory and capital costs for each component.

Items manufactured in-house (Circuit Board A and the I/O Sub C)

Judy identified several periods which had a negative unit balance where needed capacity could not be fulfilled. Judy’s approach was to identify periods with deficiency and utilize periods which had a surplus of units to be produced. Below are the results for both Items.

Circuit Board A

| PD | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Planned order releases | 0 | 0 | 79 | 200 | 200 | 200 | 400 | 400 | 400 | 200 | 0 | 0 | 0 | Actual Capacity (units) | | 300 | 300 | 200 | 200 | 200 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | Needed Capacity (units) | | 0 | 79 | 200 | 200 | 200 | 400 | 400 | 400 | 200 | 0 | 0 | 0 | Over/(Under) (units) | | 300 | 221 | 0 | 0 | 0 | 0 | 0 | 0 | 200 | 400 | 400 | 400 |

I/O Sub C | PD | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Planned order releases | 0 | 425 | 986 | 986 | 1020 | 1989 | 1989 | 1989 | 1003 | 0 | 0 | 0 | 0 | Actual Capacity | | 1000 | 1000 | 1000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | Needed Capcity | | | 425 | 986 | 986 | 1020 | 1989 | 1989 | 1989 | 1003 | 0 | 0 | 0 | 0 | Over/Under | | | 575 | 14 | 14 | 980 | 11 | 11 | 11 | 997 | 2000 | 2000 | 2000 | 2000 |

As shown in the tables above, neither item has any Past Due planned order releases therefore Judy will not need to subcontract to meet the requirements.

Component parts

Judy identified that component parts all had past due planned order releases, therefore she must expedite related purchase orders. The inventory cost, capital cost, and expediting costs are provided below.

Item | Inventory and Capital Cost per Unit for all periods | Expediting Cost for Past Due Units | Resistor B | $ 35,862.75 | $ 598,500.00 | T-former D | $ 80,873.10 | $ 1,819,200.00 | Screw E | $ 22,020.44 | $ 71,100.00 | Bolt F | $ 4,400.00 | $ 21,000.00 |…...

Similar Documents

Free Essay

Mrp, Erp, Cad/Cam

...1.0 MATERIAL REQUIREMENTS PLANNING (MRP) DEFINITION Material requirements planning (MRP) is a production planning and inventory control system used to manage manufacturing processes. It is the process that helps companies makes volume and timing calculation. Most of MRP is based on the software, sometime company use the existing software and make the new software based on the company wants. The objectives of MRP system are to: • Ensure materials are available for production and products are available for delivery to customers. • Maintain the lowest possible material and product levels in store. • Plan manufacturing activities, delivery schedules and purchasing activities. • Required goods are available when required at a right place and time. • Reduce storage and inventory holding cost and improve customer service. MRP system typically requires certain data records which the MRP programs checks and update. The chart below shows the information required to perform MRP and some of the output. Customer order record exactly what each customer has ordered, how many they ordered and when they required delivery. Forecast demand using historical data to predict future trends, cycle and seasonality is always difficult. This process is more to predict of the orders. Inventory record in MRP is to know how some of the required items already in stock. This stock may be in the progress or in raw of material. Bills of the material contains ......

Words: 1673 - Pages: 7

Free Essay

Mrp 2

...MANUFACTURING RESOURCES PLANNING What is MRP II and why it is being used Definition and History According to American Production and Inventory Control Society, MRP II can be defined as a method of the effective planning of all the resources of a manufacturing company (Higgins, Leroy and Tierney 1996). It is actually advancement or can be said as a upgrading of Material Requirement Planning System (MRP) system, which is a set of technique that uses bills of material, data and a master production schedule to calculate the requirements for materials in a manufacturing company. The MRP system was initiated in the 1960s and was spearheaded by a team of IBM innovators comprising Joe Orlicky, George Plossl and Ollie Wright who sought to create a structured methodology for planning and scheduling materials for complex manufactured products. Over the past 30 years MRP has spawned an entire industry in manufacturing and professional services. It has evolved hand in hand with technological advancements in the computer hardware industry. At the beginning, MRP systems were run on large mainframe computer costing a lot of money and required large technical staff to support them. However in the 1970s they underwent refinements that saw disparate modules get included and critical business concerns such as cost accounting and Capacity Requirements Planning get added. This gave rise to a new generation system called MRP II. Continued changes spurred by increased technological advances......

Words: 610 - Pages: 3

Premium Essay

Mrp-Toyota

...Mrp-Toyota Materials Requirements Planning (MRP) Material requirements planning (MRP) is a computer-based inventory management system designed to assist production managers in scheduling and placing orders for dependent demand items. Dependent demand items are components of finished goods—such as raw materials, component parts, and subassemblies—for which the amount of inventory needed depends on the level of production of the final product. For example, in a plant that manufactured bicycles, dependent demand inventory items might include aluminum, tires, seats, and derailleurs. The first MRP systems of inventory management evolved in the 1940s and 1950s. They used mainframe computers to explode information from a bill of materials for a certain finished product into a production and purchasing plan for components. Before long, MRP was expanded to include information feedback loops so that production personnel could change and update the inputs into the system as needed. The next generation of MRP, known as manufacturing resources planning or MRP II, also incorporated marketing, finance, accounting, engineering, and human resources aspects into the planning process. A related concept that expands on MRP is enterprise resources planning (ERP), which uses computer technology to link the various functional areas across an entire business enterprise. MRP works backward from a production plan for finished goods to develop requirements for components and raw materials.......

Words: 291 - Pages: 2

Free Essay

Sales & Opn Mrp

...on the number of components and therefore sub-component required for fulfilling the respective MPS requirements. For MRP explosion, the gross requirement are linked to parent to Planned order release for that concerned week. We are also following the lot for lot order policy (assuming a lead time of one week) However for full-fledged production of components like Delta & Epsilon, and order requirements of components Delta, Epsilon and Gamma, we have assumed that scheduled receipt for a given week in reflected in the opening inventory of the preceding week. Thus for a given week t, Planned Order Receipt (t) = Maximum (Gross Requirements (t) – Projects in hand (t-1) + Safety Stock The rationale is the inappropriate accounting of schedule receipts for calculation of MPS and to ensure sufficient inventory is built up from the start to minimize overtime requirements in the later period. Not taken Capacity Requirements Planning For capacity requirements, we have calculated the capacity (i.e. time required) using the processing time devoted towards the production process of each product or component. No sequencing has been considered in terms of waiting period. Priority Scheduling No priority is assigned to any product. Steps for DSS 1. Initialize the game 2. Press Make/Alter decisions. 3. Then make decisions for order sizing using “Use MRP”. This will populate the order fields with appropriate numbers. 4. Do not assign priority other than the......

Words: 570 - Pages: 3

Free Essay

Mrp(Manufacturing Resource Planning)

..._______________________ ------------------------------------------------- Topic: MRP II (Manufacturing Resource Planning) ------------------------------------------------- 19th October Contents Executive summary 2 Introduction and background of MRP II 3 Implement in Manufacturing Industry 6 SWOT Analysis of MRP II System 8 Conclusion 9 Recommendations (Next generation of MRP II system) 11 Reference: 13 Executive summary The purpose of this report is to illustrate what MRP II is, what features it provides, and what benefit the manufacturers could get from it as well as the existent issues in MRP II system. The research also demonstrates how MRP II was implemented in manufacturing industry by studying a case of successful implementation of MRP II software. Introduction and background of MRP II MRP II is Manufacturing Resources Planning for short. It is defined as a man machine application system for the effective planning of all resources of all manufacturing company. From the global optimal point of view, using scientific method to plan, organize, control and coordinate all the manufacturing resources and all the links of operation of enterprises effectively and reasonably is what the MRP II concerned about. The purpose of using the MRP II system is to achieve continuous and balanced production and minimize the various items in the inventory. Eventually it......

Words: 2537 - Pages: 11

Premium Essay

Mrp Theory

...demand for labour is dependent on the output the labour can produce and the revenue that can be earned from selling that output. An example of this would be an increase in demand following an increase in the productivity of workers as this would result in higher output in a shorter period of time and thus a higher potential profit to be made. Marginal physical product is the change in quantity of total product resulting from a unit change in a variable output, most often labour, keeping all other inputs unchanged. In other words, it is the extra output produced by an additional worker. MPP is one half of the MRP formula, MPP x MR. Marginal revenue product is the change in a firm’s revenue resulting from employing an additional worker and is calculated by multiplying marginal product and marginal revenue. The MRP is the demand for labour curve and thus an increase in MRP, caused by a rise in productivity or the price of the product, will cause demand for labour to rise. Elasticity of demand for labour measures the responsiveness of demand for labour in relation to a change in the wage rate. For example, an elastic demand for labour would mean that, if wages were to fall largely, firm’s demand for workers would increase. On the other hand, if wages were to increase the demand for labour is likely to decrease. Factors that influence the elasticity of demand for labour include the PED of the product and the availability of capital as a substitute to workers. Question two-......

Words: 996 - Pages: 4

Free Essay

Wilkins Mrp

...BOM L0 L1 L2 L3 1 1 2 2 3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Item Code 34-720 138N 18-860 34-850 721-11 721-16 721-20 721-3 721-300 721-30 721-80 721-90 721A-34 721-310 721-11A 721-31 721-9A 721B-34 721-33 721A-12 722-1 722-1-000 IS720 Curr OH 9600 SRs Due Qty INVENTORY RECORD Lot Sizing Rule -126000 7200 11444 648000 283500 31500 90000 -63000 216000 292500 99000 -216000 126000 216000 90000 148500 55000 55800 56413 54000 Lead Time (Days) 0 9 63 54 135 45 59 36 0 27 19 45 54 0 76 36 4 54 41 36 0 14 9 SS -1800 72000 0 22500 900 0 9000 5000 9000 3600 900 9000 5000 18000 9000 18000 9000 9000 9000 --27 10430 18533 16650 612 64372 Sep 55000 Sep Oct Nov Dec Jan 49500 49500 54900 9000 12600 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 PB5X7 PK002 PK361 RK1-720 138N 721-300 721-30 721-80 721-90 721A-34 721-310 721-11A 721-31 721-9A 721B-34 721-33 721A-12 IS720 PB5X7 482 18900 20187 4500 9 14 18 900 0 90 MPS (Ex 6 &7) Item ID 34-720 RK1-720 L2 L1 L1 722-1-000 721A-12 34-850 8/29/2005 Sep 5000 517 0 11129 50 10/03/2005 Oct 5000 662 0 10090 50 10/31/2005 Nov 5000 578 4021 8220 50 11/28/2005 Dec 4000 650 5409 6138 40 01/02/2005 Jan 4000 858 4928 5506 40 L1 IS720 12800 12040 8500 6530 6500 Item ID 34-720 Data Field Gross Requirement Scheduled Receipt Adjusted Scheduled Receipt Projected On-Hand Net Requirement Planned Order Receipt Planned Order Release 9600 SS = -8/29/2005 Sep 5000 10/03/2005 Oct 5000 Lot Size= -10/31/2005......

Words: 773 - Pages: 4

Free Essay

Mrp- Paper Review Option (Comm223)

...Student Name: Student ID: Semester: MRP- Paper Review Option (Comm223) Author(s): Van Reijmersdal, Eva Title of the Paper: Brand Placement Prominence: Good for Memory! Bad for Attitudes? Journal Title: Journal of Advertising Research. Jun2009, Vol. 49 Issue 2, p151-153. 3p Research questions: What is the audience reactions when there is a brand placement? How to affect audiences positively by using brand placement? In this article, the authors try to explain why brand placement prominence have negative effects on brand attitude under some situations and why brand placement can affect audiences’ attitudes positively through implications. Methodology used: The methodology used here would be causal research. The authors show the relationship between brand placement and audiences’ attitudes and behavior after they see a brand placement involve in a program Findings: To begin with, prominent brand placement have a high effect on brand memory, but it can cause bad brand attitudes for viewers who realized there is an advertisement. However, for the viewers who are not aware of a brand placement, they have little brand memory but a positive brand attitude. Furthermore, there is a positive effect on brand attitudes of audiences who do not like the program and a negative effect on viewers who like the program. Next, studies have shown that people can be influenced when they are not aware of a brand placement, which means that they do not have the memory of......

Words: 299 - Pages: 2

Premium Essay

Mrp Problems

...10.In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead-time is one week. Item: JOH: 40LT: 1SS: 0Q: L4L | | Week Number | | Item J | 0 | 1 | 2 | 3 | 4 | 5 | | Gross requirements | | | 75 | | 50 | 70 | | Scheduled receipts | | | | | | | | On Hand | 40 | 40 | 0 | 0 | 0 | | | Net requirements | 0 | 35 | | 50 | 70 | | | Planned order receipts | | 35 | | 50 | 70 | | | Planned order releases | 35 | | 50 | 70 | | | 11. Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units are required in Period 10. (Assume that there is currently no inventory on hand of any of these items) a. Show the bill-of-material. (Product Structure Tree) b. Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. | Period: | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | Item: | Z | Gross requirements | | | | | | | | | | 50 | OH: | 0 | Scheduled receipts | | | | | | | | | | | LT: | 2 | On-Hand Inventory from Prior Period | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | SS: | 0 | Net......

Words: 877 - Pages: 4

Premium Essay

Erp and Mrp System

...ERP system has evolved over the past thirty years. When it comes to the development of ERP, we need to review the MRP system. Generally, MRP processes specifically involve planning the use of materials necessary for manufacturing business products, so MRP is also a common function contained within an ERP [1]. ERP is an updated manufacturing resource system; it grew out of MRP II systems with relational database management, graphical user interface, and client and server architecture. In the system, the kinds of products and services offered by a company drive operation strategy. Products and services can be classified into make-to-order, make-to-stock. The MTO strategy only manufactures the end product once the customer places the order, while the MTS method forecasts demand to determine how much stock should be produced [2]. For example, Global bike incorporated produces some bikes after it received a sales order from its customers. These finished goods are used to meet customers’ need, they pertain to MTO strategy. On the other side, in the long production run, GBI may also forecast demands on the basis of sales, then produce bikes to put into inventory before customers place orders. It is an example of implement of MTS. Both MRP and ERP have their advantages and disadvantages. MRP helps to standardize business processes by offering automated methods for many areas of the business. Standardization leads to easily repeated processes and a platform for improving those......

Words: 622 - Pages: 3

Premium Essay

Mrp - Ibs Hyderabad

...Study of consumer perception about advertising in India - exploratory study on value derived by organizations from advertising Management Research Project Submitted to Prof. Subhadip Roy Submitted by 08BSHYD0035 Advait Sharma Table of Contents Project proposed 3 Objective of the project 3 Description of project in brief 3 Consumer perception perspective 3 Market perspective 5 Advertising perspective 5 Literature Review 6 Research Paper # 1 6 Research Paper # 2 6 Research Paper # 3 7 Research Paper # 4 8 Research Paper # 5 9 Research Paper # 6 10 Research Paper #7 11 Research Paper#8 11 Methodology 13 Findings and observations 16 The roles of advertising as perceived by the Public 16 The misinterpreted wide eyed view of Indian Consumers about Advertising 17 Advertising is an indicator of business health 17 Advertising size matters 18 Likely future of advertising in India 19 “Gyaan” of Advertising 20 How effective was an ad in pushing you towards first buying and then consuming a product? 20 Recommendations 22 References 25 Project proposed Study of consumer perception about advertising in India- exploratory study on value derived by organizations from advertising. Objective of the project To determine the factors that affect consumers’ perception about advertisements in the Indian context and to suggest variable approaches towards improving communicative capability of advertisements...

Words: 5619 - Pages: 23

Free Essay

Mô HìNh Mrp

...IX HOẠCH ĐỊNH NHU CẦU VẬT LIỆU I. HỌACH ĐINH NHU CẦU NGUYÊN VẬT LIỆU 1- Kỹ thuật MRP(Material Requirement Planning) là một công cụ tính tóan nhu cầu MRP là một kỹ thuật ngược chiều quy trình công nghệ để tính nhu cầu nguyên vật liệu. Nó bắt đầu từ số lượng và thời hạn yêu cầu cho những sản phẩm cuối cùng đã được xác định trong kế hoạch tiến độ sản xuất chính, đểø xác định nhu cầu các chi tiết, các bộ phận cần có để đáp ứng kế hoạch tiến độ sản xuất chính. Phương pháp này xác định số lượng, thời gian cần có các bộ phận, chi tiết và thời gian cần đặt hàng để chúng sẵn sàng khi cần đến. Đầu tiên MRP được xem như là công cụ kiểm soát tồn kho, cung cấp các báo cáo cho biết các bộ phận chi tiết nào cần phải đặt hàng, khi nào đặt hàng và hoàn thành đơn hàng. Khi sử dụng thuật ngữ này, kỹ thuật MRP chỉ là kỹ thuật tính toán nhu cầu nguyên vật liệu cho các bộ phận sán phẩm hoàn thành, không bao hàm việc sử dụng các thông tin ngược để theo dõi tiến độ thực tế các đơn hàng cũng như việc điều chỉnh các đơn hàng cho phù hợp với thực tế. 2- MRP là một hệ thống kiểm soát và hoạch định Lôgic của MRP cho phép sử dụng rộng rãi hệ thống máy tính cung cấp thông tin cho hoạch định và kiểm soát cả nguyên vật liệu lẫn năng lực sản xuất để chế tạo sản phẩm. Logic MRP được mở rộng và trở thành bộ phận then chốt của hệ thống thông tin phục vụ hoạch định, kiểm soát sản xuất và mua sắm . Thông tin mà MRP cung cấp rất có ích trong việc hoạch định tiến độ vì nó xác định những ưu tiên......

Words: 5233 - Pages: 21

Premium Essay

Mrp - Riordan Manufacturing

...New System Proposal Part 4 MRP Proposal – Overview and Scope of Work Riordan has 500 employees with a projected annual earnings of $46 million and a fortune of 1000 enterprises with revenues of $1 billion. Riordan Manufacturing has 4 worldwide locations Albany Georgia, Pontiac Michigan, Hangzhou China, and the company headquarters in San Jose. Riordan is seeking a solution to improve the tracking and management of its raw materials and finished product inventory across all its plants. The receiving, manufacturing, and shipping process throughout all Riordan plants is predominantly manual and batch oriented. These manual processes are slow, prone to error, labor intensive, and the information transfer is slow. In addition, the annual physical inventory process is very costly across all of Riordan's facilities. The annual process of inventory is not reflective of inventory on a quarterly or monthly basis. Losses to inventory of finished product, raw materials, and supplies cannot be adequately explained on an annual basis. The company’s internal stakeholders are the receiving, shipping, and sales departments, inventory clerks, and technical staff. The external stakeholders are manufacturers, suppliers, and clients. Riordan strives to continue to be an industry leader in polymer materials manufacturing and distribution. While we are only addresses some of these stakeholders with our system, the company’s overall objective is to have an ERP that wraps around their ERP,......

Words: 4025 - Pages: 17

Free Essay

Mrp-Toyota

...Requirements Planning (MRP) Material requirements planning (MRP) is a computer-based inventory management system designed to assist production managers in scheduling and placing orders for dependent demand items. Dependent demand items are components of finished goods—such as raw materials, component parts, and subassemblies—for which the amount of inventory needed depends on the level of production of the final product. For example, in a plant that manufactured bicycles, dependent demand inventory items might include aluminum, tires, seats, and derailleurs. The first MRP systems of inventory management evolved in the 1940s and 1950s. They used mainframe computers to explode information from a bill of materials for a certain finished product into a production and purchasing plan for components. Before long, MRP was expanded to include information feedback loops so that production personnel could change and update the inputs into the system as needed. The next generation of MRP, known as manufacturing resources planning or MRP II, also incorporated marketing, finance, accounting, engineering, and human resources aspects into the planning process. A related concept that expands on MRP is enterprise resources planning (ERP), which uses computer technology to link the various functional areas across an entire business enterprise. MRP works backward from a production plan for finished goods to develop requirements for components and raw materials. "MRP begins with a......

Words: 2834 - Pages: 12

Premium Essay

How Can Erp and Mrp Be Used in the Service Industry?

...included are the costs associated with making changes in capacity. Inventory holding costs must also be considered, as should storage, insurance, taxes, spoilage, and obsolescence costs. Finally, backorder costs must be computed. While difficult to measure, this generally includes expediting costs, loss of customer goodwill, and revenue loss from cancelled orders. * Develop alternative plans and compute the cost for each. * If satisfactory plans emerge, select the one that best satisfies objectives. Frequently, this is the plan with the least cost. MRP calculates and maintains an optimum manufacturing plan based on master production schedules, sales forecasts, inventory status, open orders and bills of material.  If properly implemented, it will reduce cash flow and increase profitability. CRP calculates the workload in a given department or specific work center or machine by: * Exploding the routings and processes for MRP planned and firm planned orders and updating or creating work order routings * Determining the start/due dates for each operation using: * Work center and shop calendars * Back scheduling (start date of the last operation is the due date of the previous operation) CRM, or Customer Relationship Management, is a company-wide business strategy designed to reduce costs and increase profitability by solidifying customer loyalty. True CRM brings together information from all data sources within an organization to give one, holistic......

Words: 779 - Pages: 4